"The main focus of the project is replacing the existing timber decking on the walkway, which has reached the end of its useful life. It will be replaced with glass-reinforced plastic panels, a more durable material designed to withstand heavy passenger use and last for many years."
"Engineers will also install a scaffold crash deck beneath the bridge, allowing repairs and strengthening work to be carried out from below while trains continue to run through the station. Additional improvements will include repairs to the bridge structure and replacement of the roof glazing and guttering."
"Although the footbridge will remain open, space on the walkway will be reduced as engineers work on one section at a time. Network Rail says platforms will remain accessible as normal, though passengers may experience congestion during busy periods."
Clapham Junction's footbridge is scheduled for significant refurbishment beginning March 2026 and completing November 2027. The primary work involves replacing the existing timber decking with glass-reinforced plastic panels, a more durable material suited for heavy passenger use. Engineers will install a scaffold crash deck beneath the bridge to enable repairs and structural strengthening while maintaining train operations. Additional improvements include bridge structure repairs, roof glazing replacement, and gutter work. Although the footbridge remains open throughout, pedestrian space will be reduced as work progresses section by section. Platforms stay accessible, but passengers may face congestion during peak hours. Network Rail recommends allowing an extra 10 minutes for journeys during construction, with staff present to manage pedestrian flows.
#infrastructure-maintenance #clapham-junction #footbridge-refurbishment #passenger-disruption #construction-project